The spreadsheet shows 12,000 left. The outgoing manager also knows that a supplier has completed work worth 4,000, but the invoice has not arrived. Handing over only the bank or ledger balance leaves the next manager with a misleading picture of the money available.
Use the organisation’s own accounting definitions, then build a practical bridge between the formal report and the commitments the team is managing. This is a handover aid, not a substitute for the finance system.
Put each amount in its proper stage
Separate spending that is recorded, approved but not yet invoiced, proposed but unapproved, and uncertain. For every significant commitment, identify the supplier or project, approval reference, expected amount, expected timing and person who can explain it.
In a fictional example, the report shows 12,000 unspent against the budget. If 4,000 of approved work is still to be invoiced, the manager should not treat all 12,000 as freely available. Whether and how that commitment already appears in the official report must be checked with finance so it is not deducted twice.
Hand over the exceptions
Routine invoices are often easier to trace than exceptions. Flag disputed charges, expiring quotes, recurring renewals and commitments dependent on another team’s decision. Give each exception an owner and a next action. “Someone is checking this” is not enough for a new manager to follow.
- Reconcile the handover date with the reporting period.
- Identify who can approve further spending and changes.
- Record where supporting documents are stored.
- Schedule a short follow-up after the next reporting close.
Keep private supplier or employee information in the appropriate controlled system rather than copying it into a widely shared summary. The handover should point people to evidence they are authorised to access.
Ask the incoming manager to explain the available amount and the largest unresolved commitment back to you. If the two of you reach different answers, resolve the difference before the handover is considered complete. A usable budget is one whose remaining obligations are visible, not merely one whose totals add up.